North Link Light Rail Update includes Roosevelt Station redesigns, more QFC time

Sound Transit’s December North Link Light Rail Project Update arrived our inbox today, and included a few early goodies for our stockings this holiday season.

First, the Roosevelt neighborhood QFC (6600 Roosevelt Way NE) will NOT be closing in January 2012. Due to changes in design and construction plans, Sound Transit was able to extend QFC’s lease to the end of May 2012.

The Project Update email said “[e]xtending the QFC lease will not affect the North Link project schedule,” and we have an updated construction schedule to look forward to in early 2012.

Second, a few changes in the Roosevelt Station design were revealed at the Sound Transit Board’s Capital Committee meeting on December 8. These “recent refinements” include:

  • Reducing the height and footprint of the north and south entrance facilities.
  • Expanding the public plazas bordering Northeast 66th Street to create a sense of place and reinforce opportunities for view corridors and the City of Seattle’s ‘”Green Street” program, which gives priority to pedestrian circulation and open space.
  • Moving and reducing the height of a vent structure at the south entrance to reduce view conflicts with adjacent condominium windows and balconies.

You can view these changes in the station design presentation to the Capital Committee (6.4 MB PDF).

Check out the changes in the design of the North Entrance (in this composite image we put together this afternoon):

North Entrance Design Comparison. The latest station design reveals a much smaller lobby due to overlap with the escalators/stairs, in exchange for a larger outdoor plaza area facing NE 66th Street. Plans from Sound Transit presentations, borders and dates added by Ravenna Blog.

The 60% Design Review Open House will be held sometime in Spring 2012.

North Link Light Rail update post up at Roosiehood

We’re occasionally known to do a little writing for the site next door in Roosevelt, Roosiehood. Especially when it concerns that subject near and dear to all our hearts: North Link Light Rail*.

Head on over there now to read our latest update on the North Link Light Rail project, including Sound Transit’s potential plans for a new tunnel portal location between Roosevelt and Northgate Stations.

* Roosevelt does get the station, after all.

See the future of North Link Light Rail construction, today!

Two really fun parts of the latest North Link Light Rail construction open houses for the Roosevelt and Brooklyn Stations are now available for viewing online: Illustrations of the construction sites themselves.

Enjoy!

These animations, and the presentations they were a part of, can be found on Sound Transit’s North Link Documents Library page.

Roosevelt Station Construction Open House Presentation

And now Part 2 to our Roosevelt Station Construction Open House coverage: The presentation slides themselves!


Click the Light Rail train above to view the presentation (3.6 MB PDF).

Highlights include information such as:

  • A 24-hour construction hotline number, manned by an actual person!
  • An open-to-the-public plant salvage event in early 2012 on the site of the townhouses.
  • Information on noise mitigation and lighting.
  • Probable routes for trucks entering and leaving the site.
  • Timelines for the whole project, and the next steps in the coming year.

There was also an animation of the construction site in the presentation and playing on a loop on a laptop among the open house information materials. While it is missing from the presentation above (but will be available later on the North Link Project website, here is a static glimpse of what it looks like:

If after reading over the presentation you have questions, the last slide includes contact information.

Around 100 people attended the Roosevelt Station Construction Open House on Thursday, November 3 at Roosevelt High School.

You can still access our Roosevelt Station Construction Open House Coverage: Part 1 (the live blog) here.

Roosevelt Station Construction Open House on Thursday, November 3 (archived live blog)

UPDATE (after the meeting): My live blogged session has now been archived for your reading pleasure. I will upload more information from the presentation when it becomes available from Sound Transit.

Roosevelt Station Construction Open House (11/03/2011)
6:06
Ravenna Blog:

Welcome!

Thursday November 3, 2011 6:06 Ravenna Blog
6:17
Ravenna Blog:

[Any long pauses you can chalk up to “Baby Issues.”]

Thursday November 3, 2011 6:17 Ravenna Blog
6:22
Ravenna Blog:

I would guesstimate about 60+ people here so far, taking in the open house portion. Large poster boards up around the perimeter, outlining the construction areas, affected parts of the neighborhood, etc. Pictures later.

Thursday November 3, 2011 6:22 Ravenna Blog
6:30
Ravenna Blog:

Presentation starts at 6:30. Sound Transit generally makes the presentation slides available within a few days of the event.

Thursday November 3, 2011 6:30 Ravenna Blog
6:31
Ravenna Blog:

Ooo! There are paper craft light rail trains!

Thursday November 3, 2011 6:31 Ravenna Blog
6:33
Ravenna Blog:

North Link Deputy Project Director Ron Endlich is starting off the presentation portion now.

Thursday November 3, 2011 6:33 Ravenna Blog
6:35
Ravenna Blog:

After Intro is Roosevelt Station Construction info, then Next Steps, Q&A, and back to Open House.

Thursday November 3, 2011 6:35 Ravenna Blog
6:36
Ravenna Blog:

Overview of the whole system now. I’ll be sticking to the Roosevelt-specific info.

Thursday November 3, 2011 6:36 Ravenna Blog
6:41
Twitter
RavennaBlog:

Live blogging the Roosevelt Station Construction meeting. Follow along at http://ravennablog.com. [via Twitter]

Thursday November 3, 2011 6:41 RavennaBlog
6:43
Ravenna Blog:

Excavation to start in early 2013. There will be a 24-hour construction hotline, manned by an actual person, for answering questions.

Thursday November 3, 2011 6:43 Ravenna Blog
6:46
Ravenna Blog:

Mid-2012 will see the start of demolition, and the beginning of the onslaught of trucks into the neighborhood.

Thursday November 3, 2011 6:46 Ravenna Blog
6:48
Ravenna Blog:

Excavation and tunneling from 2013-2017. Some parking lost on 66th and 67th, some sidewalks to be closed.

Thursday November 3, 2011 6:48 Ravenna Blog
6:50
Ravenna Blog:

If you’d like a real world example of what the construction site will look like, head up to the Capitoll Hill Station site. Wall will be very similar.

Thursday November 3, 2011 6:50 Ravenna Blog
6:52
Ravenna Blog:

There will be night work, and a variance will need to be granted. Another construction meeting to follow with more specifics.

Thursday November 3, 2011 6:52 Ravenna Blog
6:55
Ravenna Blog:

Routes that the trucks will take to and from the construction site will depend on whether the trucks will be heading north or south from the site.

Thursday November 3, 2011 6:55 Ravenna Blog
6:58
Ravenna Blog:

Parking, sidewalks and streets near the site will remain affected during station construction (post-tunnel boring).

Thursday November 3, 2011 6:58 Ravenna Blog
7:01
Ravenna Blog:

Q&A time now. (There’s LOTS more to the presentation, but the presenter was speedy. I’ll be sure to hunt down the slides later for you.)

Thursday November 3, 2011 7:01 Ravenna Blog
7:03
Ravenna Blog:

12th Ave NE will remain open during construction, but the parking lane on the west side will be taken for construction/truck traffic.

Thursday November 3, 2011 7:03 Ravenna Blog
7:05
Ravenna Blog:

Good ? about repairs to roads affected by the toll of heavy truck use. Sound Transit will be the one to repair, should streets need it. Would work with SDOT.

Thursday November 3, 2011 7:05 Ravenna Blog
7:05
Twitter
brucenourish:

No meeting, however seemingly mundane of a topic, is ever boring in Roosevelt. [via Twitter]

Thursday November 3, 2011 7:05 brucenourish
7:08
Ravenna Blog:

Yes, parking will be affected, but workers will be parking off-site. So, that will help. Some.

Thursday November 3, 2011 7:08 Ravenna Blog
7:11
Ravenna Blog:

Parking at the station question. No, no additional parking for the station. Idea is to walk to the stations or use transit. Residential Parking Zones could be created/expanded.

Thursday November 3, 2011 7:11 Ravenna Blog
7:11
Twitter
brucenourish:

Petitioner wants ST to attempt to save some “sacred” trees that ST has already determined cannot be transplanted. [via Twitter]

Thursday November 3, 2011 7:11 brucenourish
7:21
Ravenna Blog:

QFC sounds like they’ll be closing in January. Staff will be relocated to other stores, but the store itself will NOT be relocated.

Thursday November 3, 2011 7:21 Ravenna Blog
7:24
Ravenna Blog:

The excavation and tunneling portion of construction s a 24/7 affair. 12 trucks per hour is the estimate. And as I understand it from an earlier meeting, that would be dump trucks with trailers (doubles).

Thursday November 3, 2011 7:24 Ravenna Blog
7:26
Ravenna Blog:

Worry about property values dropping during construction. Thought is gain after completion would outweigh.

Thursday November 3, 2011 7:26 Ravenna Blog
7:27
Ravenna Blog:

7 months to excavate the station. 20 months to tunnel (to the stadium, I believe).

Thursday November 3, 2011 7:27 Ravenna Blog
7:30
Ravenna Blog:

About 100 people here, by the way.

Thursday November 3, 2011 7:30 Ravenna Blog
7:32
Ravenna Blog:

40-50 feet a day is the speed of the boring machines. That’s where the 20 months comes from.

Thursday November 3, 2011 7:32 Ravenna Blog
7:32
Ravenna Blog:

230 tunnel easements for North Link total.

Thursday November 3, 2011 7:32 Ravenna Blog
7:34
Ravenna Blog:

Exact route of the North Link tunnels not yet known, but current mapped route is within a half a block of the final, says Ron.

Thursday November 3, 2011 7:34 Ravenna Blog
7:37
Ravenna Blog:

Ooo, some rage against the machines that have no luggage racks. (The trains don’t have them.)

Thursday November 3, 2011 7:37 Ravenna Blog
7:40
Ravenna Blog:

And now back to the open house portion. And, hey! Peaks is handing out free cone coupons!

Thursday November 3, 2011 7:40 Ravenna Blog
8:38

Ravenna Blog Social Media Round-Up for October 23-29

Good news! The tool that we use to create these weekly updates has gone though an upgrade, making it much easier to grab stories from not only twitter, but facebook, RSS feeds, and much much more!

Henceforth, we’ll be calling this weekly post the “Social Media Round-Up” to reflect this enhanced collectibility of good local Internet stuff.

ENJOY.

Light Rail, Community Center, Superintendent meetings (and more!)

Ah, autumn: The crisp air, the bright colored foliage, the opportunity to keep warm by huddling together with your neighbors at community meetings (many of which include snacks).

Here is a list of community meetings being held in the first half of November. As always, we recommend attending them all. However, if you can only choose one, we’d steer you toward the Advisory Council/Community Meeting at the Ravenna-Eckstein Community Center. Your input into the future of center operations — prior to the big budget decisions happening in City Hall in November — is vital.

  • Tuesday, November 1: Ravenna-Bryant Community Association Board Meeting, Ravenna-Eckstein Community Center (6535 Ravenna Ave NE), 7-9 PM. All neighbors are welcome to attend. Agenda to come.
  • Tuesday, November 1: Mayor’s Town Hall, Nathan Hale High School (10750 30th Ave NE), 5:30-8 PM. Mayor Mike McGinn, City Departments & Community Groups will answer your questions and hear what’s on your mind.
    (5:30-6:30 Meet and Greet: City Departments and local community organizations have information tables, answer questions and offer volunteer opportunities; 6:30-6:40 Youth performance- 6:40-8:00 Open question and answer session with the Mayor)
  • Thursday, November 3: North Link Light Rail Roosevelt Station Open House, Roosevelt High School Commons (1410 NE 66th Street), 6-8:30 PM (presentation starts at 6:30 PM). The open house will focus on the nuts and bolts of construction plans (NOT station design plans) at Roosevelt Station.
  • Wednesday, November 9: Advisory Council/Community Meeting, Ravenna-Eckstein Community Center (6535 Ravenna Ave NE), 6:30-8:30 PM. Input sought from community members about future use and operating hours of the RECC in 2012. Staff present from the RECC and the new Northeast Geographic team, as well as members of Parks and Recreation leadership, talking about how well parks is meeting our needs in the Ravenna-Eckstein community. Child care and light refreshments available.
  • Monday, November 14: Community Meeting on the Permanent Superintendent of Seattle Public Schools, Roosevelt High School (1410 NE 66th Street), 7-8:30 PM. National search for a new Superintendent, or hire Interim Superintendent Dr. Susan Enfield? Input sought from members of the public. (Survey available in mid-November as well.) Childcare and light snacks will be available starting at 6:30 PM. Hosted by the Seattle Council PTSA.
  • Wednesday, November 16: North Link Light Rail Brooklyn Station Open House, Neptune Theatre (1303 NE 45th St), 6-8:30 PM (presentation starts at 6:30 PM). The November open house will focus on the nuts and bolts of construction plans at Brooklyn Station.

____________________

If we’re missing any other community meetings in early November on this list, do let us know. We’re happy to add them.

Roosevelt Station 30% Design Open House (audio and documents included)

20110527-120432.jpg

From L to R: Map of Sound Transit's current service and future projects, stickers from the campaign to bring Light Rail INTO the Roosevelt neighborhood, and information on the Roosevelt Station

A crowd of around 150 people attended last night’s Roosevelt Station design open house at the Ravenna-Eckstein Community Center (6535 Ravenna Ave NE), where Sound Transit staff presented the 30% completion designs for the structure and were on hand to answer questions.

Missed the meeting, and would like the next best thing? I recommend viewing the Roosevelt 30 Percent Design Presentation while listening to the Part 1 audio. The rest of the documents, graphics, and audio from the meeting can be found below.

___________________________

A 30-minute informal open house-style period was followed by a presentation (which included a question and answer time).

The presentation portion will be made available by Sound Transit (in PDF form), and are also found on the North Link Documents Library page.

Future meetings about the station will include open houses at both 60% and 90% completion of the design. There will also be a meeting to outline how the construction phase will take place (this fall), and a separate meeting for those people whose property will be tunneled under as construction proceeds (once the tunnel route has been set, also this fall).

20110527-120553.jpg

Graphic showing the footprint of Roosevelt Station (orange) and two parcels to be used during construction to be open to development when construction is completed (yellow).

Puget Sound transit guru Atomic Taco (his internet handle) was in the audience, live tweeting the more major points during the meeting. (You can visit his Flickr site here.) While the audio recording above and the presentation docs to follow will be useful to those who missed last night’s meeting, Atomic Taco’s and my tweets are also worth a read (and are much easier to skim through).

What follows is a selection of our tweets during the meeting. (At the bottom of the window, hit the “Load more…” link to continue reading.)

Soil sample drilling continues for North Link Light Rail

Earlier this week, whilst driving east on Ravenna Blvd, I happened upon the following scene in the grassy median (at Ravenna Blvd and 12th Ave NE):

20110427-133523.jpg

A few tweets and emails later, I get the scoop about the digging from Bruce Gray, who does media relations for Sound Transit:

Yes, that work is part of our advance geotechnical work for the North Link project to extend light rail from UW to Northgate.

The crew you saw, or are seeing, on Ravenna near 12th are taking soil samples to give us an idea of the type of materials we will encounter during tunneling for that extension. This is all part of the final design work for the alignment. We take soil samples along the entire alignment to get something akin to an underground profile of conditions the tunnel boring machines could encounter. The line is scheduled to open in 2021.

Bruce was also kind enough to reply in an earlier North Link Light Rail post to a commenter regarding the proposed names of the stations. (You can read his reply here.)

Twitter Feed Round-Up for August 14

Ack! It’s been a while. Time for another Ravenna Blog Twitter Feed Round-Up.

[If you can’t understand why people find twitter to be so fascinating/addicting, I made a comment last night about seeing lots of police cars go by on NE 75th St, and then watched the whole Wedgwood QFC shooting story unfold, in near real time, on twitter. Beat that, local TV news.]

Most recent at the top:

  • Sand Point @MetMarket now carrying California Olive Ranch olive oil. As local an olive oil as you can get, for now. #climatechange
  • There’s also a depressing University Link Light Rail Countdown Clock. 2268 days, 15 hours, 46 minutes and counting. Oy.
  • The @seatransitblog post on PSRC funding recommendations includes a pic of the Roosevelt Light Rail Station: http://bit.ly/bZRT28
  • You CAN download an “I vote!” icon, however. They know you miss that sticker. http://www.kingcounty.gov/elections/widgets.aspx
  • Ballots need to be in the MAIL by tomorrow: No drop-offs at Neighborhood Service Centers. Can’t tweet your choices to @kcnews, either.
  • Eight chickens for everyone! As long as they’re ≥10 feet from primary residential structures, and aren’t boys.
  • Recycle week. Yay.
    Seattle can drop trash to every other week as long as recycling becomes weekly.
    IMHO.
  • @sallybagshaw is now following us. Triple word score! http://www.youtube.com/watch?v=wDcem5dpFwY #harassingnewestfollower
  • Also, NE 45th St Viaduct Project: the flickr set – http://www.flickr.com/photos/sdot_photos/sets/72157624263204995/
  • SDOT Update: 22nd Ave NE to NE 45th St to reopen by Saturday! SDOT still on track to reopen the NE 45th St viaduct by September 10!
  • Dahl Park Wading Pool closes for the year on Thursday, August 19th (last day). “But MOOOOOM (and @SeattleParks) – Summer just started!”
  • Story on @Crosscut about Sisleyville and development – Roosevelt’s dilemma: How should a neighborhood grow? http://tinyurl.com/3xj5m45
  • 50 facebook followers! Number 50 is the guy who needs the garage. Really gotta find him a garage now.
  • McSweeney’s (John Flowers) recommends “The Newspaper” as best e-reader on the market. Hats! http://www.mcsweeneys.net/2010/8/11flowers.html
  • Field trip! Gonna ride the light rail to Columbia City, get ourselves some Tutta Bella, South. Can’t wait until 2020 for lunch today.

My personal favorite:

  • Driving by 15th Ave NE & NE 65th St this morning, my TWO-AND-A-HALF YEAR OLD asks when those buildings will be torn down. #Sisleyville